Champions Bridge Replacement & Alum Creek Bank Stabilization
Progress Update: Champions Bridge Replacement and Bank Stabilization Project Manager, Chris Thompson. All hands were on deck ** for this one! Great job guys. Summer ’23.
Progress Update: Champions Bridge Replacement and Bank Stabilization Project Manager, Chris Thompson. All hands were on deck ** for this one! Great job guys. Summer ’23.
PROJECT UPDATE: GALLIA COUNTY Summer ’23.
PROJECT COMPLETION: O.P. CHANEY GRAIN ELEVATOR The historic grain elevator in Canal Winchester, OH recently finished up the roofing portion of work. The previous roof was installed in the 1960’s and needed a replacement. Righter Company teamed up with Accurate Roofing, Inc. to give the building a new standing seam metal roof. Brandon Lowery is […]
PROJECT UPDATE: GALLIA COUNTY The first phase of the deck pour has been completed. The crew for the bridge consists of Foreman – Jeff McGuire, Butch Sullivan, Ben Sullivan, Jeremy McGuire, Brenton McGuire, Lee Sullivan, Jordan Sullivan, JC Durham, and Robert Ward. Stay tuned for more updates! Summer ’23.
https://fb.watch/qwhbcpMsEi/ The Righter Company’s Mark Litter (Project Foreman) captured some footage of Operator, Justin Adams, driving piling for the falsework of the bridge. In the video you can see laborers, Pete Litter and Matt Mitchell, as well as Dannie Wilson, operating in the background. Summer ’23.
PROJECT: TURNBERRY GOLF COURSE – EMERGENCY BRIDGE REPAIRS The Righter Company, Inc. was contacted by the City of Columbus to repair damages at Turnberry Golf Course. Their bridge that accesses the golf course had the abutments partially washed out causing the structure to shift. Work included driving piling next the existing super structure, installing a […]
PROJECT UPDATE: HILLS COVERED BRIDGE Currently at the Hills Covered Bridge in Marietta, OH, Brandon Lowery and his crew, Clay Slevin, Dakota Lowery, and Rob Richmond, are working on the timber truss rehabilitation. 10 newly fabricated thrust blocks have been delivered to the project for incorporation into the timber truss rehabilitation. There are some additional […]
PROJECT UPDATE: URBANA BOOSTER STATIONS Progress is still being made for our Urbana Booster Stations project. The installation of 8″ ductile iron pipe at the Children’s Home site started last week. Nick Miller – Project Manager, Tom Ison – Superintendent, Crew Members – Josh Priest, Brayden Ison & Shawn Ison. Summer ’23.
The Righter Company was contacted to install helical piers at the McWane Ductile Facility in Coshocton, Ohio. 27 each, round shaft helical piers were installed with new construction caps to complete the project. John Fuller was the foreman on the project with a crew consisting of Clay Slevin, Kasey McCloskey, and Bobby Sharp. Jacobi Schmalenberger […]
PROJECT UPDATE: ODOT 210603 – GALLIA COUNTY The concrete patching of the bridge superstructure is ongoing. Most of the vertical patching on the through girders has been completed, with the remaining vertical patches to be completed over the next 2 weeks. The end floor beams have been removed, and the new ones will be poured […]