https://fb.watch/qwhbcpMsEi/ The Righter Company’s Mark Litter (Project Foreman) captured some footage of Operator, Justin Adams, driving piling for the falsework of the bridge. In the video you can see laborers, Pete Litter and Matt Mitchell, as well as Dannie Wilson, operating in the background. Summer ’23.

News
February 29, 2024

Turnberry Golf Course – Emergency Bridge Repairs

PROJECT: TURNBERRY GOLF COURSE – EMERGENCY BRIDGE REPAIRS The Righter Company, Inc. was contacted by the City of Columbus to repair damages at Turnberry Golf Course. Their bridge that accesses the golf course had the abutments partially washed out causing the structure to shift. Work included driving piling next the existing super structure, installing a […]

News
February 29, 2024

Hills Covered Bridge

PROJECT UPDATE: HILLS COVERED BRIDGE Currently at the Hills Covered Bridge in Marietta, OH, Brandon Lowery and his crew, Clay Slevin, Dakota Lowery, and Rob Richmond, are working on the timber truss rehabilitation. 10 newly fabricated thrust blocks have been delivered to the project for incorporation into the timber truss rehabilitation. There are some additional […]

News
February 29, 2024

Urbana Booster Stations

PROJECT UPDATE: URBANA BOOSTER STATIONS Progress is still being made for our Urbana Booster Stations project. The installation of 8″ ductile iron pipe at the Children’s Home site started last week. Nick Miller – Project Manager, Tom Ison – Superintendent, Crew Members – Josh Priest, Brayden Ison & Shawn Ison. Summer ’23.

News
February 29, 2024

McWane Pole Casting – Helical Piers

The Righter Company was contacted to install helical piers at the McWane Ductile Facility in Coshocton, Ohio. 27 each, round shaft helical piers were installed with new construction caps to complete the project. John Fuller was the foreman on the project with a crew consisting of Clay Slevin, Kasey McCloskey, and Bobby Sharp. Jacobi Schmalenberger […]

News
February 29, 2024

Gallia County

PROJECT UPDATE: ODOT 210603 – GALLIA COUNTY The concrete patching of the bridge superstructure is ongoing. Most of the vertical patching on the through girders has been completed, with the remaining vertical patches to be completed over the next 2 weeks. The end floor beams have been removed, and the new ones will be poured […]

News
February 29, 2024

Urbana Booster Stations

PROJECT START: URBANA BOOSTER STATIONS Project Manager, Nick Miller, has started a new project with the City of Urbana working on two Booster Stations. The project will consist of the installation of two new prepackage booster stations and associated waterline work. Currently Tom Ison — Superintendent, Crew members — Shawn Ison, Josh Priest, and Brayden […]

News
February 29, 2024

Moeller Hall Foundation Repair

PROJECT START: Moeller Hall Foundation Repair The Righter Company has been busy working on foundation repairs up at Columbus State Community College Delaware Campus. Work includes underpinning the existing foundation and installation of resistance piers. The foreman on the project is Butch Sullivan and crew consists of Ben Sullivan, Kaiden Weaks, JC Durham, and Damien […]

News
February 29, 2024

Greene County Pump Stations

PROJECT UPDATE: GREENE COUNTY PUMP STATIONS The Righter Company’s, Nick Miller, working along with Greene County for Greene County Pump Stations – Grange Hall and Indian Ripple. Recently the concrete pour at Indian Ripple has been completed. This is the building pad for the new booster station that will be installed later this year. The […]