PROJECT UPDATE: ODOT 210603 – GALLIA COUNTY
The concrete patching of the bridge superstructure is ongoing. Most of the vertical patching on the through girders has been completed, with the remaining vertical patches to be completed over the next 2 weeks. The end floor beams have been removed, and the new ones will be poured in the next 2 weeks. Removal and replacement of the bridge deck will begin soon. Crew consists of Jeff McGuire, Jeremy McGuire, Brenton McGuire, Jordan Sullivan and Lee Sullivan; Project Manager, Mike Killilea. Summer ’23.