June 24, 2020

Out With The Old In Fayette County

On June 23, the Righter crew working on ODOT 194026 were removing parts of the old bridge.  The project consists of the removal and replacement of the existing superstructure, the modification of the existing bridge abutments and piers and roadway approach work.  ODOT awarded Righter a $1,615,127 contract last October for this work, which began in late February of this year.  The current completion date is 10/31/20.  The Project Manager is Mike Killilea and the Field Supervisor is Jerry McVey.  Field crew is Dannie Wilson, Ben Sullivan, Butch Sullivan, Jordan Sullivan and Derick Bendickson.

 

News, News (AutoPost)
About Mike Killilea